Bosnodig
- Project Number:
- FNL-L-004
- Pathway:
- Land Stored Carbon
- Methods:
- Food forest
- Size:
- 1.5 ha
- Remover:
- Bosnodig
- Location:
- Voorst
- Start date:
- 2023
Total
342tCO2for this project
Available
259tCO2Holding
69tCO2Carbon calculation
The calculation behind this project's ledger, shown exactly as published in its calculation sheet (updated 20 Dec 2024).
Projected storage
storage potential per ha x area
LCA emissions
project related emissions
Net storage potential
project storage -/- emissions over 20 years
Credits issued 20-12-2024
of 214 credits first 12 years, 43 kept back in the holding pool
General information
Remover name
Project code
Project name
Location
Area
Duration
estimated permanence of removal and storage
Holding pool
freed up when measurements confirm projection pathways
Project emissions
LCA estimate, or specified when >20%
Per hectare
Baseline TEC
Above Ground, Below Ground and Soil Organic Carbon, following CDM AR-ACM0003
Reference capacity
Using CEDA and Soil sample data
Storage potential
Projection -/- baseline
Per project
Projected storage
storage potential per ha x area
LCA emissions
project related emissions
Net storage potential
project storage -/- emissions over 20 years
Removal credits issued
Credits first 12 years
12/20 x net storage potential
Holding Pool
20% of the first 12 years
Credits issued 20-12-2024
80% of the first 12 years
Source: Carbon Credit Calculation Bosnodig 2 - the published calculation is the underlying evidence for the Ledger figures. Values are shown as published, without reformatting.