Bamboerin
- Project Number:
- BBR-L-001
- Pathway:
- Land Stored Carbon
- Methods:
- Bamboo farms
- Size:
- 3.2 ha
- Remover:
- Bamboerin VOF
- Location:
- Hulsel
- Start date:
- 2023
Total
491tCO2for this project
Available
393tCO2Holding
98tCO2Carbon calculation
The calculation behind this project's ledger, shown exactly as published in its calculation sheet (updated 19 Mar 2026).
Projected storage
storage potential per ha x area x storage duration 100 year equivalent
LCA emissions
project related emissions
Net storage potential
project storage -/- emissions over 20 years
Credits issued
of 491 credits first 12 years, 98 kept back in the holding pool
General information
Remover name
Project name
Location
Project code
Area
Start year
year of planting
Duration
estimated permanence of removal and storage
Holding pool
freed up when measurements confirm projection pathways
Project emissions
LCA estimate, or specified when >20%
Per hectare
Baseline TEC
Soil Organic Carbon and Above Ground Carbon, following CDM AR-ACM0003
Reference capacity
Using CEDA and Soil sample data
Storage potential
Projection -/- baseline
Per project
Projected storage
storage potential per ha x area x storage duration 100 year equivalent
LCA emissions
project related emissions
Net storage potential
project storage -/- emissions over 20 years
Removal credits issued
Credits first 12 years
12/20 x net storage potential
Holding Pool
20% of the first 12 years
Credits issued
Source: Carbon Credit Calculation - the published calculation is the underlying evidence for the Ledger figures. Values are shown as published, without reformatting.