DERIX Production
- Project Number:
- DERIX-C-001
- Pathway:
- Construction Stored Carbon
- Methods:
- Biobased product
- Size:
- 4025 m³
- Remover:
- Derix Group
- Location:
- Dam 63, D-41372 Niederkrüchten, Germany
- Start date:
- 2023
Total
3099tCO2units in circulation
for this project
for this project
Available
52tCO2Units available for purchase, both concept and delivered
Holding
155tCO2Construction Stored Carbon
Date | Type | Vintage | From | To | Holding | Potential | Delivered | Available | Trading | (Pre)Purchased ¹ | ID | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
2025-05-22 | Draft | |||||||||||
2025-05-22 | Potential | +58 | +1111 | +1111 | ||||||||
2025-07-02 | Trader In | Any | WDL-Gruppe | -556 | +556 | |||||||
2025-08-21 | Trader In | Any | EDEKA-MIHA Immobilien-Service GmbH | -426 | +426 | |||||||
2025-08-21 | Draft | |||||||||||
2025-08-21 | Potential | +97 | +1833 | +1833 | ||||||||
2025-08-21 | Trader In | Any | The Cradle GmbH & Co. KG | -705 | +705 | |||||||
2025-09-03 | Purchase | Any | W. u. J. Derix GmbH & Co. | -517 | +517 | |||||||
2025-09-03 | Purchase | Any | Poppensieker & Derix GmbH & Co. KG | -688 | +688 |
Project Totals: | 155 | 2944 | 0 | 52 | 1687 | 1205 |