Gemeentehuis Krimpenerwaard
- Project Number:
- KRIMP-C-001
- Pathway:
- Construction Stored Carbon
- Methods:
- Biobased building
- Size:
- 2 m³
- Remover:
- Gemeente Krimpenerwaard
- Location:
- Provincialeweg 5a, 2861 EB Bergambacht
- Start date:
- 2024
- Certification status:
- Pre-validated
Total
1204tCO2for this project
Available
1144tCO2Holding
60tCO2Carbon calculation
The calculation behind this project's ledger, shown exactly as published in its calculation sheet (updated 16 Mar 2026).
Total Construction Stored Carbon
Net Carbon Removal Benefit
the project's net removal after deductions, as published by the tool
Project details
Adress
Project type
Expected realisation year
Project lifespan
Gross floor area
Project phase
Net Carbon Removal Benefit
Total Construction Stored Carbon
Net Carbon Removal Benefit
the project's net removal after deductions, as published by the tool
Per m2 gross floor area
Total lifespan (including reuse)
Biobased products
CLT (Cross Laminated Timber)
quantity 230 m3, lifespan 50 years
CLT (Cross Laminated Timber)
quantity 383 m3, lifespan 50 years
CLT (Cross Laminated Timber)
quantity 6 m3, lifespan 50 years
LVL (Laminated Veneer Lumber)
quantity 261,12 m3, lifespan 50 years
CLT (Cross Laminated Timber)
quantity 112,92 m3, lifespan 50 years
CLT (Cross Laminated Timber)
quantity 138,72 m3, lifespan 50 years
Lignatur 320 mm
quantity 1103,36 m3, lifespan 50 years
OSB
quantity 29,724 m3, lifespan 100 years
WISA
quantity 39,762 m3, lifespan 50 years
Cyclin akoestisch 60mm
quantity 750 m2
Source: Climate_Cleanup_NCRB_CalculationTool_v3.2_Gemeentehuis Krimpenerwaard.xlsx (tab “Report”) - the published calculation is the underlying evidence for the Ledger figures. Values are shown as published, without reformatting.