Lidl Capelle aan den IJssel
- Project Number:
- LIDL-C-001
- Pathway:
- Construction Stored Carbon
- Methods:
- Biobased building
- Size:
- 345 m³
- Remover:
- Lidl Nederland GbmH
- Location:
- Capelle aan den IJssel, Schermerhoek 509-513.
- Start date:
- 2025
- Certification status:
- Pre-validated
Total
261tCO2units in circulation
for this project
for this project
Available
248tCO2Units available for purchase, both potential and delivered
Holding
13tCO2Construction Stored Carbon
Carbon calculation
The calculation behind this project's ledger, published as a document (updated 21 May 2026). It is shown exactly as published.
Source: NCRB_LIDL-C-001.pdf - the published calculation is the underlying evidence for the Ledger figures. It is shown as published, without reformatting. More files are on the Documents tab.