Scave Portugal Reforest

Project Number:
SCVL003
Pathway:
Land Stored Carbon
Methods:
Regenerative farming
Size:
14.6 ha
Remover:
Scave
Location:
Portugal
Start date:
2024

Total

2269tCO2
units in circulation
for this project

Available

1815tCO2
Units available for purchase, both concept and delivered

Holding

454tCO2
Land Stored Carbon

Carbon calculation

The calculation behind this project's ledger, shown exactly as published in its calculation sheet (updated 15 Mar 2026).

Projected storage

4.727tCO2

storage per ha x area

LCA emissions

945tCO2

project related emissions

Net storage

3.781tCO2

project storage -/- emissions over 20 years

Credits issued

1.815credits

of 2.269 credits first 12 years, 454 kept back in the holding pool

General information

Remover name

Bart van Beuzekom

Project code

SCVL003

Project name

Scave Portugal Reforest

Location

Cidadelhe(Pinhel), Portugal

Area

14,60ha

Duration

estimated permanence of removal and storage

100years

Correction rocky soil

Correction factor for soil-less area (rocks)

30%

Holding pool

freed up when measurements confirm projection pathways

20%

Project emissions

LCA estimate, or specified when >20%

20%

Per hectare

Baseline TEC

Below Ground and Soil Organic Carbon, following CDM AR-ACM0003, excl above ground carbon

134tCO2/ha

Target TEC

Using CEDA and Soil sample data

596tCO2/ha

Storage

Storage -/- baseline

463tCO2/ha

Per project

Projected storage

storage per ha x area

4.727tCO2

LCA emissions

project related emissions

945tCO2

Net storage

project storage -/- emissions over 20 years

3.781tCO2

Removal credits issued

Credits first 12 years

12/20 x net storage potential

2.269credits

Holding Pool

20% of the first 12 years

454credits

Credits issued

1.815credits

Source: Carbon Credit Calculation Scave Portugal Reforest - the published calculation is the underlying evidence for the Ledger figures. Values are shown as published, without reformatting.